As part of the LIFE Danube Floodplains project, in addition to BROZ, also the project partner VODOHOSPODÁRSKA VÝSTAVBA, state enterprise deals with water regime restoration.
Works on D2a weir started in autumn. Construction of culvert will ensure flow of water into the currently dry branch which is connecting the Bodícke and Šulianske river branch. Below the culvert there will be a significant water jump. Mitigation of the impact on fish migration and stability of the bottom of the banks below the culvert will therefore be ensured by technical solutions. The culvert will be fortified with a stone wall and equipped with adjustable gates.
Also within this reconstruction site, the requirements of boaters were taken into account. The project will include accessible ramps to move between the water and the river bank.